RAILWORKS FAMILY OF COMPANIES:
RailWorks constructed the track infrastructure and grade crossing signal protection to service the new ethanol plant.
RailWorks constructed 6,390 feet of track, using 112-lb. relay rail on wood ties, and installed insulated joints for bonding and grounding at the load-out points. In addition to furnishing and constructing four #8 turnouts, one mainline turnout and 240 feet of direct-fixation track in the process buildings, RailWorks also designed and installed a 40-foot concrete crossing with signal protection